Framework under old plaster ceiling
Uriage shipyard
Reliable and without cracking.
The generally accepted structural movements are absorbed by the metal framework.
Variations in temperature and relative humidity do not cause variations
dimensional plates.
BENEFITS
For new or old sites.
Low load under floors.
Integration of pipelines.
High performance.
Elimination of the risk of cracking
Screw for the top of the rod, 6mm diameter threaded rod, jumper,
fur (f530) or (s47).
Secure the eyebolt in the beam with a screwdriver, drill with mandrel.
Beam to be searched with hammer
old plaster ceiling
120 cm max
Beam
Floor
Rider
(pivot)
please wait for a few moments
Ceiling on furring (F530 or S47), plasterboard in BA 13 mm. The framework
on the frame must be done with eyebolts screwed every 60cm
maximum (2 BA 13, 50 cm) between the axes of the furs. Along the fur, the
ankles must be at most every 1.30m.
Threaded rods diameter 6, length 1 or 2 m
Threaded rod of diameter 6, cut to the desired length, to receive the pivot. Lay the furs, then the glass wool, to finish the plasterboards.
Clip the furs on the jumpers (pivot)
200mm Vapor Barrier Glass Wool
In the case of insulation coated with a vapor barrier, the continuity of the vapor barrier is ensured by a taped strip.